Electrical grids aren’t keeping up with the green energy push. That could risk climate goals
View
Date:2025-04-17 15:32:33
FRANKFURT, Germany (AP) — Stalled spending on electrical grids worldwide is slowing the rollout of renewable energy and could put efforts to limit climate change at risk if millions of miles of power lines are not added or refurbished in the next few years, the International Energy Agency said.
The Paris-based organization said in the report Tuesday that the capacity to connect to and transmit electricity is not keeping pace with the rapid growth of clean energy technologies such as solar and wind power, electric cars and heat pumps being deployed to move away from fossil fuels.
IEA Executive Director Fatih Birol told The Associated Press in an interview that there is a long line of renewable projects waiting for the green light to connect to the grid. The stalled projects could generate 1,500 gigawatts of power, or five times the amount of solar and wind capacity that was added worldwide last year, he said.
“It’s like you are manufacturing a very efficient, very speedy, very handsome car — but you forget to build the roads for it,” Birol said.
If spending on grids stayed at current levels, the chance of holding the global increase in average temperature to 1.5 degrees Celsius above pre-industrial levels — the goal set by the 2015 Paris climate accords — “is going to be diminished substantially,” he said.
The IEA assessment of electricity grids around the globe found that achieving the climate goals set by the world’s governments would require adding or refurbishing 80 million kilometers (50 million miles) of power lines by 2040 — an amount equal to the existing global grid in less than two decades.
Annual investment has been stagnant but needs to double to more than $600 billion a year by 2030, the agency said.
It’s not uncommon for a single high-voltage overhead power line to take five to 13 years to get approved through bureaucracy in advanced economies, while lead times are significantly shorter in China and India, according to the IEA.
The report cited the South Link transmission project to carry wind power from northern to southern Germany. First planned in 2014, it was delayed after political opposition to an overhead line meant it was buried instead. Completion is expected in 2028 instead of 2022.
Other important projects that have been held up: the 400-kilometer (250-mile) Bay of Biscay connector between Spain and France, now expected for 2028 instead of 2025, and the SunZia high-voltage line to bring wind power from New Mexico to Arizona and California. Construction started only last month after years of delays.
On the East Coast, the Avangrid line to bring hydropower from Canada to New England was interrupted in 2021 following a referendum in Maine. A court overturned the statewide vote rejecting the project in April.
veryGood! (2)
Related
- A White House order claims to end 'censorship.' What does that mean?
- Beset by Drought, a West Texas Farmer Loses His Cotton Crop and Fears a Hotter and Drier Future State Water Planners Aren’t Considering
- Jamie Foxx Takes a Boat Ride in First Public Appearance Since Hospitalization
- In Pakistan, 33 Million People Have Been Displaced by Climate-Intensified Floods
- Federal hiring is about to get the Trump treatment
- This Program is Blazing a Trail for Women in Wildland Firefighting
- Apple moves into virtual reality with a headset that will cost you more than $3,000
- Chimp Empire and the economics of chimpanzees
- Trump suggestion that Egypt, Jordan absorb Palestinians from Gaza draws rejections, confusion
- In a Strange Twist, Missing Teen Rudy Farias Was Home With His Mom Amid 8-Year Search
Ranking
- Taylor Swift Eras Archive site launches on singer's 35th birthday. What is it?
- Experts raised safety concerns about OceanGate years before its Titanic sub vanished
- The Largest U.S. Grid Operator Puts 1,200 Mostly Solar Projects on Hold for Two Years
- Inside Clean Energy: Yes, There Are Benefits of Growing Broccoli Beneath Solar Panels
- A Mississippi company is sentenced for mislabeling cheap seafood as premium local fish
- When big tech laid off these H-1B workers, a countdown began
- 'What the duck' no more: Apple will stop autocorrecting your favorite swear word
- Saudi Arabia cuts oil production again to shore up prices — this time on its own
Recommendation
A Mississippi company is sentenced for mislabeling cheap seafood as premium local fish
This $41 Dress Is a Wardrobe Essential You Can Wear During Every Season of the Year
Candace Cameron Bure Responds After Miss Benny Alleges Homophobia on Fuller House Set
The missing submersible raises troubling questions for the adventure tourism industry
Most popular books of the week: See what topped USA TODAY's bestselling books list
¿Por qué permiten que las compañías petroleras de California, asolada por la sequía, usen agua dulce?
California Passes Law Requiring Buffer Zones for New Oil and Gas Wells
Inside Clean Energy: This Virtual Power Plant Is Trying to Tackle a Housing Crisis and an Energy Crisis All at Once
Like
- Trump suggestion that Egypt, Jordan absorb Palestinians from Gaza draws rejections, confusion
- Despite Misunderstandings, Scientists and Indigenous Peoples in the Arctic Have Collaborated on Research Into Mercury Pollution
- Boeing finds new problems with Starliner space capsule and delays first crewed launch